Press Information Bureau · All India · 20 Sept 2026

Indian Railways Approves ₹133 Crore for Construction of Four-Lane Road Over Bridge on Udhna-Ukai Songadh Section of Western Railway

Indian Railways has approved a four-lane Road Over Bridge on the Udhna-Ukai Songadh section of Western Railway, replacing Level Crossing No. 53 at Km 62/2-4. The total cost is ₹133.2295 crore, shared between Indian Railways and the State Government. The project includes an Open Web Girder bridge, viaduct, and railway approach sections.

Key facts
  • The total cost of the four-lane ROB is ₹133.2295 crore, shared between Indian Railways (₹66.6147 crore) and the State Government (₹66.6148 crore).
  • The ROB will replace Level Crossing No. 53 at Km 62/2-4 on the Udhna-Ukai Songadh section of Western Railway.
  • The crossing location has a 62% skew, increasing design and construction complexity.
  • The viaduct portion will have a total length of 311.58 metres with an estimated cost of ₹19.98 crore.
  • The Railway Approach (RE) portion will have a length of 524.32 metres with an estimated cost of ₹10.25 crore.

Summary written by Suchna Board from the official release; the release itself is the source.

Advertisement
Read the official release
Indian Railways Approves ₹133 Crore for Construction of Four-Lane Road Over Bridge on Udhna-Ukai Songadh Section of Western Railway · Suchna Board